On 25 July 2016, the ZUE learnt of the Company’s submission of the lowest price tender in the tender procedure for: “Completion of construction works on the Ostrowite – Biskupiec Pomorski and Biskupiec Pomorski – Jamielnik routes as part of the following project: "Works on the line no. 353 of the Jabłonowo Pom - Iława - Olsztyn – Korsze section."
Contracting Authority: PKP Polskie Linie Kolejowe S.A.
Net value of the tender submitted by the Company: PLN 27.9m – the amount does not include the provisional sum of 4% of the tender net value (PLN 1.1m).
Gross value of the tender submitted by the Company (including the provisional sum): PLN 35.7m.
The project completion date according to the specifications has been set at 4 December 2017. However, according to the tender submitted by the Company, the project will be completed 60 days before the abovementioned date.