On 11 August 2016, ZUE learnt of the Company’s submission of the lowest price tender in the tender procedure for: Design and completion of construction works in the area of the Medyka station in connection with the following project: “Investment works at the Medyka - Mościska II border crossing."
Contracting Authority: PKP Polskie Linie Kolejowe S.A.
Net value of the tender submitted by the Company: PLN 41.5m.
Gross value of the tender submitted by the Company: PLN 51.0m.
The project completion date (the completion of all the works covered by the contract) is 1300 days of the contract conclusion date (not later than 20 May 2020).