Contract with PKP PLK S.A.

ZUE S.A. inform about the contract signed on 17 September 2019 by the Company and PKP Polskie Linie Kolejowe S.A. The contract deals with the project named: Preparation of design documentation and completion of construction works in connection with the project named: LOT D – Works on the railway lines no. 131, 542 and 739 of the Rusiec Łódzki (km 137.500) – Zduńska Wola Karsznice (km 170.212) section as part of the Infrastructure and Environment Operational Programme (IEOP) 5.1-14 “Works on the railway line C-E 65 of the Chorzów Batory – Tarnowskie Góry – Karsznice – Inowrocław – Bydgoszcz – Maksymilianowo section.” (the “Contract”).

The Contract net value including the provisional sum: PLN 582.7m.

The Contract gross value: PLN 716.7m.

Completion of the tasks under the Contract: 41 months of the Contract conclusion date.